Risk Register

The main delivery, technical, data, AI and sustainability risks, how likely and serious each is, and how each will be reduced.

For: Leadership & funderEngineeringGovernance & legalStatus: Draft v0.1Updated: 29 October 2026

In short

  • Fifteen risks across delivery, data, technology, AI, adoption and sustainability, each with a likelihood, impact, mitigation and owner.
  • The highest-rated: slow data-sharing agreements (R1), weak source data or APIs (R2), low adoption (R3), procurement delays (R6), county power and connectivity (R8), staff turnover (R9) and no recurrent budget (R10).
  • Risks are reviewed at every steering committee and at each gate.

Why it matters

Most risks that would sink RADAR are not technical — they are agreements, people, procurement and money. Naming them early, with an owner and an early-warning sign, turns surprises at a gate review into issues handled months earlier.

How this document connects

Labels used in this document: Proposal stated in the funded proposal, stage-gate paper or deck · Research external evidence (see Sources) · Recommended proposed design choice, to be confirmed · Open decision still needed

1Risk map

R4 R5 R7 R11 R12 R13 R14 R15 R3 R6 R10 R2 R8 R9 R1 Low Low Medium Medium High High LIKELIHOOD → IMPACT →
Risk map. Likelihood (across) against impact (up), before mitigation. Risks in the top-right cells get a named owner and are reviewed at every steering committee and gate; details and mitigations are in the register below.

2Register

Ratings are before mitigation (L = likelihood, I = impact; L/M/H). Initial assessment Recommended — the steering committee owns the ratings.

IDRiskLIMitigationEarly warningOwner
R1Data-sharing agreements and approvals take longer than planned, delaying live data and the MVPHHStart month 1; standard DSA template; KNPHI-led umbrella agreement; DPIA lodged early; MVP can demo on de-identified replays while agreements finishNo signed DSA for an MVP source by month 3KNPHI + WSU
R2Source data incomplete, late, or without usable APIHMIntegration ladder (start at L1); data-quality dashboard; feedback to custodians; pick MVP sources by readinessInventory shows < 2 seasons of history or no exportWSU engineering
R3Low adoption: officers see RADAR as extra workMHRemove re-typing; champions; SOP update; SUS and time-on-task tracked; fast supportFalling log-ins; back-entered decisions risingCGP + KNPHI
R4Unsafe AI recommendation contributes to a missed or delayed escalationLHRules set the level; validator; human confirmation; FN ceiling; kill switch; incident reviewOverride reasons citing wrong levelUM/CGHE + KNPHI
R5Security incident or data breachLHZones, MFA, encryption, audit, pen test, minimum-necessary data, incident runbookFailed-login spikes; unpatched critical CVEsWSU + KNPHI ICT
R6Server/GPU procurement or import delaysMHOrder in month 1–2; develop on cloud with synthetic data meanwhile; consider Government hosting as interimNo PO by month 2WSU finance
R7Recruitment delays (coordinator, analyst, enterprise partner)MMEarly recruitment Proposal; interim cover from partnersPosts unfilled at month 2WSU
R8Power and connectivity failures at county EOCsHMStarlink, UPS, light UI, SMS alerts, offline forms, paper fallbackReadiness assessment scoresCGP + counties
R9EOC staff turnover erodes skillsHMToT, job aids, six-monthly refreshers, onboarding pack, in-app guidanceShare of active users trained < 80%CGP
R10No recurrent budget after October 2029MHCost model from Gate 2 data; engage KNPHI finance early; open-source stack; align with national budget calendarNo budget line in KNPHI submission by mid-2029PI + KNPHI
R11Regulatory change or DHA certification delaysMMEarly DHA engagement; FHIR validation in CI; track regulationsNew DHA requirements issuedWSU + DHA liaison
R12Enterprise software partner selected late or under-scopedMMSelect in months 1–2 with clear statement of work tied to Gate 1 and 2 deliverablesNo contract by month 3WSU
R13A major outbreak diverts EOC staff from the projectMMRapid-response mode: use the outbreak as live validation where safe; keep a minimal core team on deliveryLevel 3 activationSteering committee
R14Model performance drifts on real dataMMMonitoring, retraining procedure, disaggregated reportingRising override rateUM/CGHE
R15Scope creep toward “integrate everything”MMMVP scope locked; new sources only via the prioritisation criteria; change control in TWGUnplanned connectors in sprint plansPI + TWG

3How risks are managed

  1. Review rhythm. Top risks at every TWG; full register at every steering committee and in each gate evidence pack.
  2. Escalation. Any risk rated High/High, or any early-warning sign that fires, goes to the steering committee within two weeks.
  3. Issues vs. risks. When a risk happens it becomes an issue with an action plan and date; the register records the outcome.
  4. Gate link. If a risk threatens the MVP deadline, the 30-day remediation notice to the foundation applies (doc 13).

4Key assumptions

If any of these turns out false, revisit the plan.

  • KNPHI can nominate a system owner, data stewards and ICT staff from the start.
  • At least four MVP sources can share data at Level 1–2 by March 2027.
  • KNPHI/DHA will authorise a production hosting location by mid-2027.
  • The DMT-PHE trigger-card set is stable enough to encode for the MVP.
  • Sobek can provide a GHEC-AI interface for joint specification in the MVP phase.

Sources

  • INV-110654 proposal — Budget (spending risks and mitigations), Data Access.
  • Stage-gate paper — MVP remediation rule.
  • Risk ratings are an initial assessment for the steering committee to confirm.