Partners, Roles & Project Governance

Who the partners are, who owns which workstream, the RACI for key decisions and the meeting rhythm that keeps the project on track.

For: Leadership & funderEngineeringEOC & surveillanceStatus: Draft v0.1Updated: 29 October 2026

In short

  • KNPHI owns RADAR and is its primary user; DHA sets standards and hosting rules; WSU holds the grant and leads integration.
  • Each partner owns a distinct workstream: UM/CGHE the AI-enabled DMT-PHE, CGP deployment, KEMRI evaluation, KIPRE One Health, an enterprise partner product hardening, Sobek the GHEC-AI interface.
  • A RACI table assigns who decides, who does the work, and who must be consulted for each major deliverable.
  • Three standing bodies keep decisions moving: steering committee, technical working group, data governance group.

Why it matters

RADAR crosses institutions that own different data, systems and mandates. Without clear ownership, decisions stall between partners — especially the MER standard, data access and model releases. Clear roles also make the KNPHI transition at Gate 3 a handover of something KNPHI already runs, not a surprise.

How this document connects

Labels used in this document: Proposal stated in the funded proposal, stage-gate paper or deck · Research external evidence (see Sources) · Recommended proposed design choice, to be confirmed · Open decision still needed

1Who is who

GOVERNMENT STEWARDSHIP CONSORTIUM WORKSTREAMS GOVERNANCE BODIES Gates Foundation funder · INV-110654 WSU Global Health – Kenya prime · grant holder · PI grant KNPHI owner · primary user · PHEOC · DMT-PHE steward Digital Health Agency (DHA) standards · hosting · certification WSU MER, fusion layer, connectors, APIs/MCP, TPP, evaluation lead UM / CGHE AI-enabled DMT-PHE, guardrails, containers CGP national/county rollout, training, helpdesk KEMRI ethics, baseline/endline, data quality KIPRE One Health linkages, stakeholders Enterprise partner (TBD) UI/UX, load & security testing, hardening Sobek · GHEC-AI response hand-off interface Steering committee quarterly · gates Technical WG fortnightly · design Data governance monthly · access, DSAs Consultants KNPHI data governance · MEL
Who is who. KNPHI (with DHA) owns the system and the decisions; WSU holds the grant and leads integration; each partner owns a distinct workstream. Three standing bodies (right) keep decisions moving between quarterly reviews.
PartnerWorkstream Proposal
KNPHIGovernment lead, system custodian and primary operational user; data/system access; DMT-PHE stewardship; EOC and county workflow integration; operational transition and institutionalisation
Digital Health Agency (DHA)National digital architecture, interoperability standards and FHIR alignment; hosting, cybersecurity, data-residency and production deployment guidance; alignment/certification in Kenya's digital health ecosystem
WSU Global Health – KenyaPrime; scientific/technical coordination and grant oversight; MER, data-fusion layer, connectors, APIs/MCP and user-facing RADAR; TPP/product coordination; formal evaluation leadership
University of Michigan (CGHE)AI-enabled DMT-PHE lead: agentic decision-support architecture and integration; benchmarking, safety guardrails and responsible-AI validation; containerisation, interfaces and ongoing maintenance
CGP — Center for Global Health and Pandemic IntelligenceDeployment and operationalisation: national/county DMT-PHE rollout and EOC workflow integration; training, simulation, mentorship and helpdesk; adoption monitoring and scale-up lessons
KEMRIEvaluation and implementation science: epidemiology, ethics/research governance; baseline/endline evaluation, data-quality assessment and validation; analysis of detection-to-decision, usability and 7-1-7
KIPRE — Kenya Institute of Primate ResearchOne Health integration and stakeholder engagement: animal, wildlife and environmental surveillance linkages; cross-sector workflow validation; policy engagement
Enterprise software partner (to be selected early; budgeted under the enterprise software consultant line)Product engineering, UI/UX, scalability and load testing, cybersecurity, production hardening, deployment support
Sobek (GHEC-AI)Joint RADAR/DMT-PHE–GHEC-AI interface specification and integration
ConsultantsKNPHI data-governance consultants; MEL consultant; enterprise software consultant

2Core team and effort

WSU-funded personnel as stated in the proposal (effort per year). Proposal

RolePersonEffortFocus
Principal InvestigatorDr Isaac Ngere15%Scientific and technical leadership; KNPHI and county coordination; validation of outputs
Director, East Africa Finance & OperationsSelestine Njoga7%Stakeholder engagement, financial compliance, M&E oversight
Project CoordinatorTo be recruited70%Day-to-day management, milestones, logistics, reporting, training
Senior Software EngineerKadenge Wa Ya35%Leads platform development and systems integration
Data Analyst(s)To be recruited50%Harmonisation, quality, dashboards, AI-output validation, MEL evidence
MEL consultantRobert Osoti—Implementation monitoring, performance tracking, evaluation support
Engineering capacity

WSU's in-house engineering effort is one senior engineer at 35%. Delivering the MER, connectors, analytics integration and UI by June 2027 depends on the enterprise partner and UM/CGHE starting early. Selecting the enterprise partner in the first two months is on the critical path. Recommended

3Who decides what (RACI)

R = responsible (does the work) · A = accountable (decides) · C = consulted · I = informed. Starting proposal Recommended.

Deliverable / decisionKNPHIDHAWSUUMCGPKEMRIKIPREEnt.Sobek
MER standardACRCCCCIC
Technical Product Profile & architectureACRRIIIRC
Connectors & data flowsCCA/RIIICRI
AI agent & guardrailsCICA/RCCICI
Model release to productionAICRCCIII
Data-sharing agreements & DPIAACRIICCIC
Hosting & security sign-offACRCIIIRI
Site rollout & trainingAICCRICCI
GHEC-AI interfaceACRCCIICR
Baseline & endline evaluationCIACCRCII
Gate evidence pack & reportingCIA/RCCCCII
Transition to KNPHIACRRCIIRI

4Governance bodies and rhythm

Proposed structure Recommended; the proposal budgets inception, annual review and stakeholder meetings. Proposal

BodyMembersCadenceDecides
Steering committeeKNPHI (chair), DHA, WSU PI, partner leads; foundation as observerQuarterly + at each gateScope, priorities, gate submissions, risks above threshold, transition
Technical working groupWSU engineering, UM/CGHE, enterprise partner, KNPHI ICT and data, DHA technical, Sobek as neededFortnightlyArchitecture decisions (ADRs), MER changes, release readiness
Data governance groupKNPHI data-governance consultants, source custodians, KEMRI, WSUMonthlyAccess requests, agreements, DPIA, data classes, incidents
Annual partners meetingAll partners, countiesYearlyReview progress and lessons; plan next year

5Document owners

Suggested owner for each document in this set. Recommended

DocumentsOwner
01 Overview · 13 Roadmap · 16 Budget · 17 RisksWSU PI with the project coordinator
02 Landscape · 05 Interoperability · 03 MERWSU senior software engineer with KNPHI data team
04 Architecture · 11 Security & infrastructureWSU senior software engineer with enterprise partner and KNPHI ICT
06 Intelligence layerWSU data analyst with KNPHI epidemiologists
07 DMT-PHE & agent · 12 Responsible AIUM/CGHE lead
08 Workflow · 09 DeploymentCGP lead with KNPHI PHEOC
10 Data governanceKNPHI data-governance consultants
14 MELMEL consultant with KEMRI
15 Partners · 18 Glossary · 00 Start hereProject coordinator

6Open questions

  1. Enterprise partner selection — scope, procurement route and start date. Owner: WSU · month 1–2
  2. Sobek agreement — terms for the interface, data handling and hosting. Owner: WSU + KNPHI
  3. KNPHI counterparts — named system owner, data stewards and ICT lead who will run RADAR after transition. Owner: KNPHI · kick-off

Sources

  • INV-110654 proposal — Investment details; Budget (personnel and consultants).
  • RADAR deck — slide 14 “RADAR partnership model”.
  • Stage-gate paper — Gate 1 milestone 2 (TPP sign-off parties).