Doc 14·Delivery & Management

Monitoring, Evaluation & Learning

Learning questions, exact metric definitions, where each number comes from, and the baseline-to-endline evaluation design.

For: M&E / researchLeadership & funderEOC & surveillanceStatus: Draft v0.1Updated: 29 October 2026

In short

  • Four learning questions: Is it faster? Is it more accurate and usable? Do multiple streams add intelligence? Does the GHEC-AI hand-off work?
  • Every indicator has one exact definition, one data source and one owner — most come straight from RADAR's own timestamps and logs.
  • Design: baseline before deployment, routine monitoring, endline near the end; mixed methods; internally led by WSU with KNPHI.
  • Evidence feeds three decisions: gate go/no-go, model recalibration, and scale-up policy.

Why it matters

The gates are judged on numbers. If “concordance” or “detection-to-classification time” are defined loosely, two people can compute different answers from the same data — and a gate can be missed on a technicality or passed without real improvement. Precise definitions agreed now also protect the credibility of the two planned publications.

How this document connects

Labels used in this document: Proposal stated in the funded proposal, stage-gate paper or deck · Research external evidence (see Sources) · Recommended proposed design choice, to be confirmed · Open decision still needed

1Learning questions

#Question ProposalMain evidence
LQ1Does RADAR reduce time from signal detection to DMT-PHE classification and escalation?MER timestamps, baseline vs. post-deployment
LQ2Does it improve concordance with expert classification, documentation completeness, 7-1-7 performance and user acceptability?Parallel runs, expert panel, decision logs, SUS
LQ3Does integrating multiple streams give earlier or additional actionable intelligence, and what technical, workflow or safety challenges affect adoption and scale-up?Signal cards (which stream first), back-testing, interviews
LQ4Does the RADAR/DMT-PHE–GHEC-AI hand-off work — reliability, completeness, timeliness, user experience, effect on mobilisation?Interface logs, response timestamps, interviews

2From evidence to decisions

DATA SOURCES MER timestamps Audit & override log Expert-panel reviews SUS & user surveys Interviews, observation Data-quality reports METRICS Detection → classification 7-1-7 compliance AI-expert concordance False-negative rate Documentation completeness Dataset integration % LEARNING QUESTIONS LQ1 Faster? LQ2 More accurate & usable? LQ3 Multi-stream adds value? LQ4 GHEC-AI hand-off works? DECISIONS Gate go / no-go Retrain / recalibrate Scale-up & policy
From raw evidence to decisions. Most numbers come from data RADAR already writes (MER timestamps, audit and override logs), so measurement adds little burden. Each metric answers a learning question, and the answers feed the gate, retraining and scale-up decisions.

3Indicator reference sheet

Definitions are proposals for the MEL protocol Recommended; targets are from the stage gates Proposal.

IndicatorDefinitionSourceTarget
Signal → classification timeMedian (and IQR) hours from detected_at to first human-confirmed classified_at, for verified eventsMER≤ 48 h (Gate 2)
Detection → escalation latencyMedian hours from detected_at to first escalated_at at Level ≥ 2MERReduction vs. baseline
7-1-7 compliance% of events meeting each target separately (detect ≤ 7 d, notify ≤ 1 d, respond ≤ 7 d) and all three togetherMER, Early Action ReviewsImprovement vs. baseline (Gates 2–3)
AI–expert concordance% of assessed events where AI-supported level = panel reference level; plus weighted kappaParallel runs, panel0.85 / 0.88 / 0.90
False-negative rate% of panel Level 2–3 events classified lower by the AI-supported pathParallel runs, panelBelow ceiling (set at Gate 1)
Documentation completeness% of required DMT-PHE fields completed across escalation events (required set fixed in the protocol)Decision log80% / 85% / 90%
Adverse decision eventsCount of reviewed incidents meeting the agreed definition (doc 12)Incident logZero
System Usability ScaleStandard 10-item SUS, 0–100, per siteUser survey75 / 78 / 80
Dataset integration% of baseline-inventory datasets at integration Level ≥ 2 with monitored automated flowsConnector registry≥ 80% (Gate 2)
Additive intelligence% of verified events where a non-human stream (animal, climate, OSINT) signalled first, and median lead timeMER links, signal cardsReported (LQ3)
Hand-off performance% of authorised responses with a complete hand-off; median time authorisation → team mobilisedInterface logs, MERReported (LQ4)

4Evaluation design

  1. Baseline (before deployment). At the national EOC, reconstruct detection-to-classification, detection-to-escalation and 7-1-7 for recent events from existing records — a Gate 1 milestone that cannot be redone later. Proposal Repeat at each county before its go-live. Recommended
  2. Routine monitoring. Indicators computed automatically from MER and logs; monthly dashboard; quarterly review.
  3. Parallel runs. Eight weeks per site generating concordance datasets (doc 09).
  4. Endline. Toward the end of the grant: the same measures, plus surveys, key-informant interviews and workflow observation. Proposal
  5. Analysis. Pre/post comparison per site; where enough events exist, an interrupted time-series design; qualitative analysis of adoption barriers.
Independence

The formal evaluation is internally led by WSU with KNPHI rather than by an independent third party. Proposal To strengthen credibility: pre-register the protocol and analysis plan, keep the expert panel independent of the build team, have KEMRI lead data-quality assessment, and invite an external reviewer to audit the endline analysis. Recommended

Watch for small numbers

Level 2–3 events are uncommon. At some sites there may be too few real events in a period for stable estimates. Report confidence intervals, pool across sites where appropriate, and supplement with simulation cases — clearly labelled as such.

5Data collection and ethics

  • System-generated data (timestamps, logs) under KNPHI data-custodian approval.
  • Surveys, interviews and observation with informed consent or an approved waiver through the KEMRI ethics process. Proposal
  • Casual research assistants (budgeted in periods 1 and 3) support data collection and quality checks.

6Reporting and dissemination

OutputAudienceWhen
Monthly indicator dashboardSteering committee, EOC managersMonthly from MVP
Gate evidence packsGates FoundationProgress reports 1–2, final report
Annual partners meetingKNPHI, counties, partnersYearly (budgeted)
Two peer-reviewed manuscripts + preprintsScientific communityBy Gate 3
Scale-up evidence report and policy briefMoH, KNPHI, counties, fundersBy Gate 3
Regional disseminationAfrica CDC networks, WHO Preparedness Data ExchangeYear 3

7Open questions

  1. Which past events form the baseline, and over what period? Owner: MEL consultant + KNPHI · month 2
  2. Required DMT-PHE fields for the completeness measure. Owner: KNPHI + CGP
  3. Will an external reviewer audit the endline? Owner: PI

Sources

  • INV-110654 proposal — Measurement and Evaluation; formal evaluation; outcome measures.
  • Stage-gate paper — thresholds and Gate 3 milestones 1, 4–6.
  • 7-1-7 Alliance — FAQ.
  • MeasuringU — Interpreting SUS scores.