Doc 16·Delivery & Management

Budget & Resources

The US$1.5M budget by category and period, the team's level of effort and the cost questions to settle early.

For: Leadership & funderStatus: Draft v0.1Updated: 29 October 2026

In short

  • Total request US$1,500,000: US$1,335,968 direct and US$164,032 indirect (12% rate stated).
  • Subawards to partners are the largest line (US$800,000 cumulative), then WSU personnel and benefits (US$308,941) and consultants (US$157,838).
  • Technology spend is small: one enterprise server (US$36,095), hosting (US$4,000 in each of Periods 1 and 3) and Starlink connectivity.
  • Three things to settle early: how the line items reconcile to the total, whether the server includes a GPU, and what KNPHI will need to fund after 2029.

Why it matters

The budget determines what can be built in-house versus by partners, how much hardware the AI layer gets, and whether the system can be sustained after the grant — a Gate 3 condition (“documented KNPHI recurrent budget pathway”). Spotting reconciliation and scope gaps now is cheaper than at a progress report.

How this document connects

Labels used in this document: Proposal stated in the funded proposal, stage-gate paper or deck · Research external evidence (see Sources) · Recommended proposed design choice, to be confirmed · Open decision still needed

1Headline figures

$1.50M

Total requested Proposal

$1.34M

Total direct costs

$164K

Indirect costs (12% rate)

53%

Share of total going to subawards

2Where the money goes

Subawards (cumulative) Subawards (cumulative): US$800,000 (53% of US$1.5M) $800,000 Personnel & benefits Personnel & benefits: US$308,941 (21% of US$1.5M) $308,941 Indirect costs (12%) Indirect costs (12%): US$164,032 (11% of US$1.5M) $164,032 Consultants Consultants: US$157,838 (11% of US$1.5M) $157,838 Other direct costs (P1–P3) Other direct costs (P1–P3): US$74,025 (5% of US$1.5M) $74,025 Enterprise server (Dell R770) Enterprise server (Dell R770): US$36,095 (2% of US$1.5M) $36,095 Travel Travel: US$31,797 (2% of US$1.5M) $31,797
Where the US$1.5M goes (as stated in the proposal). Subawards to consortium partners are over half the budget; WSU personnel and indirect costs are the next largest lines. Hover a bar for its share. The stated line items sum to more than the total — see the reconciliation note below.
LineUS$Share of $1.5MWhat it buys
Subawards (cumulative)800,00053.3%Partner workstreams: AI-enabled DMT-PHE, deployment and training, evaluation, One Health integration
Personnel & benefits308,94120.6%PI, finance & operations, project coordinator, senior software engineer, data analyst(s)
Indirect costs164,03210.9%WSU overheads
Consultants157,83810.5%KNPHI data-governance consultants, MEL consultant, enterprise software consultant (hardening, scalability, security, hosting review)
Other direct costs (periods 1–3)74,0254.9%ICT supplies, training materials, connectivity, hosting, field and meeting costs
Enterprise server (Dell PowerEdge R770)36,0952.4%Primary hosting for RADAR, databases, analytics and AI services
Travel31,7972.1%County visits, reviews, workshops, two international conferences
Sum of stated lines1,572,728104.8%See reconciliation note
Reconciliation note

The stated lines add up to US$72,728 more than the US$1.5M total. The direct-cost total (US$1,335,968) leaves US$727,272 for subawards once the other direct lines are subtracted — and US$727,272 plus 10% is exactly US$800,000. The likeliest explanation is that the subaward figure is quoted including subrecipients' own indirect costs. Also, US$164,032 is 12.3% of the stated direct total rather than exactly 12%. Confirm both against the detailed budget narrative before the first financial report. Open

3Other direct costs by period

PeriodUS$Main items Proposal
Period 1 — design, governance, infrastructure32,153ICT supplies for staff and KNPHI, training materials ($4,013), hosting subscription ($4,000), Starlink for KNPHI ($1,900), casual staff ($6,720), ethics fees ($1,000), community engagement, airtime
Period 2 — deployment, training, validation18,244Participant reimbursements ($4,800), connectivity ($2,850), airtime and fuel ($2,400 each), ICT accessories, partners meeting, vehicle costs
Period 3 — evaluation, dissemination, transition23,628Research assistants ($6,720), ICT supplies ($4,000), annual hosting ($4,000), connectivity ($2,850), dissemination, participant reimbursements, partners meeting
Total74,025

4Payments and gates

Payment 2 is released at Gate 1 (Progress Report 1) and Payment 3 at Gate 2 (Progress Report 2); no payment is attached to Gate 3. Proposal A held gate therefore delays cash for the following period — keep partner subaward schedules aligned with gate dates. See doc 13.

5Technology cost observations

  • GPU. On-premise LLM inference needs at least one data-centre GPU. If the US$36,095 server quote does not include one, either re-scope the server, budget a GPU from savings, or use a Government-authorised hosted model. Open
  • Single server. No line covers a second node or recovery site. Explore DHA/Government shared infrastructure for disaster recovery (doc 11).
  • Software licences. The recommended stack is open source, so there are no licence lines — the costs are people and hardware.
  • Penetration testing and load testing (Gate 2) should be explicitly costed, for example within the enterprise software consultant line.

6After the grant: the recurrent budget pathway

Gate 3 requires a documented KNPHI recurrent budget pathway reflected in a budget submission or departmental statement. Proposal Cost categories to estimate from Gate 2 operating data Recommended:

CategoryExamples
PeopleSystem owner, 1–2 platform engineers, data steward(s), analyst, helpdesk share
InfrastructurePower, cooling, rack space, hardware warranty and refresh (5-year cycle), GPU refresh
ConnectivityEOC internet and backup links at national and county sites
SecurityAnnual penetration test, certificates, security monitoring
TrainingRefreshers and onboarding to offset staff turnover
Model upkeepPeriodic re-evaluation and retraining; knowledge-base curation

7Spending risks

From the proposal Proposal, with mitigations in doc 17: recruitment delays for key staff, ICT procurement lead times, slower-than-expected stakeholder adoption, and technical integration challenges between surveillance systems.

8Open questions

  1. Reconcile subaward and indirect figures with the budget narrative. Owner: WSU finance · month 1
  2. Does the server include a GPU? Owner: WSU finance + engineering · month 1
  3. Subaward split between UM/CGHE, CGP, KEMRI and KIPRE, and its alignment with gate timing. Owner: WSU

Sources

  • INV-110654 proposal — Investment details; Budget section (all line items and period breakdowns).
  • Stage-gate paper — payments attached to Gates 1 and 2; Gate 3 milestone 3.