Roadmap & Stage Gates
The three-year plan from MVP to KNPHI transition, the three funding gates, their milestones and the thresholds that must be met.
In short
- Three years, three stage gates: Gate 1 (MVP + national validation, to Sep 2027), Gate 2 (county deployment, to Sep 2028), Gate 3 (evaluation + transition, to Sep 2029, verified at the final report). Payments are attached to Gates 1 and 2.
- The four-component MVP is a hard internal deadline: accepted by KNPHI by 30 June 2027. A partly delivered MVP cannot pass Gate 1.
- Thresholds rise at each gate: concordance 0.85 → 0.88 → 0.90; SUS 75 → 78 → 80; documentation completeness 80% → 85% → 90%.
- A few figures differ between the proposal, the stage-gate paper and the deck — they are listed here to settle at kick-off.
Why it matters
Payments are tied to gates, and each gate asks for evidence of both product quality (accuracy, usability) and real-world effect (7-1-7, latency). Planning backwards from those tests — especially the MVP deadline and the pre-deployment baseline, which cannot be recreated later — is the difference between passing on time and asking for a remediation window.
How this document connects
← Builds on
01 · Project OverviewThe outcomes promised in the proposal become the stage-gate thresholds.09 · Deployment & AdoptionSite rollout is the core of Gate 2.12 · Responsible AIConcordance, SUS and adverse-event thresholds are gate criteria.14 · MEL FrameworkMEL produces the evidence each gate is judged on.15 · Partners & GovernanceThe governance structure decides who signs off each gate.16 · Budget & ResourcesFunding is released per gate and period.17 · Risk RegisterOpen risks are reviewed at every gate decision.Informs →
—1Three-year timeline
| Proposal phase | Content | Stage-gate mapping |
|---|---|---|
| Phase 0 · months 1–6 | MVP: agreed MER; initial data flows for priority sources; integrated DMT-PHE workflow (ingest → classify → escalate → human confirmation); initial RADAR/DMT-PHE–GHEC-AI interface specs with Sobek | Gate 1 · Nov 2026 – Sep 2027 · Progress Report 1 · Payment 2 |
| Phase 1 · months 7–12 | Platform preparation, dataset inventory and mapping, priority connectors, outbreak user guides, national DMT-PHE deployment plan, TPP and architecture, GHEC-AI interface prototype, 8-week national parallel run | |
| Phase 2 · year 1–2 | Deployment and parallel validation at national and five county EOCs; site readiness, ICT, training; AI retraining; hardening, load and security testing; deployment on KNPHI/DHA infrastructure | Gate 2 · Oct 2027 – Sep 2028 · Progress Report 2 · Payment 3 |
| Phase 3 · year 2–3 | Prospective evaluation, endline, scale-up evidence and policy brief, KNPHI operational transition, regional dissemination (Africa CDC, WHO) | Gate 3 · Oct 2028 – Sep 2029 · Final report |
2Gate 1 — MVP delivered and platform validated
Reporting period November 2026 – September 2027. Decision: proceed to national and county deployment, or hold and remediate. Proposal
Milestones
- RADAR MVP demonstrated and accepted by KNPHI by June 2027, with all four components (MER; functioning data flows for priority sources; integrated DMT-PHE workflow; GHEC-AI interface specifications agreed with Sobek).
- Technical Product Profile and architecture signed off by WSU, UM/CGHE, KNPHI/DHA and the enterprise software partner.
- Dataset inventory and system mapping complete; priority connectors and API/MCP interfaces working; outbreak user guides drafted for all four categories; national DMT-PHE deployment plan approved.
- Eight-week parallel validation at the national EOC completed, generating a concordance dataset against independent expert-panel review.
- Governance conditions met: KEMRI SERU amendment, WSU IRB extension, data-sharing agreements/MOUs for all MVP data streams.
- Baseline measured and reported: detection-to-classification time, detection-to-escalation latency and 7-1-7 compliance at the national EOC before RADAR deployment.
Thresholds
- AI–expert concordance ≥ 0.85 on the parallel-validation dataset
- SUS ≥ 75 among national EOC users
- DMT-PHE documentation completeness ≥ 80% across escalation events
- Zero adverse decision events attributable to the AI layer
- Minimum event record agreed with KNPHI and in operational use
- Baseline 7-1-7 and detection-to-classification measures documented and agreed
If the MVP is not accepted by 30 June 2027, the consortium notifies the foundation within 30 days with a remediation plan — not waiting for the progress report. Gate 1 cannot be passed on a partially delivered MVP, because Gate 2 depends on all four components. Proposal
3Gate 2 — Deployed, hardened and validated in operational use
Reporting period October 2027 – September 2028. Decision: proceed to prospective evaluation and KNPHI transition, or hold scale-up. Proposal
Milestones
- RADAR and AI-enabled DMT-PHE in routine use at the national EOC and five priority county EOCs, with readiness assessments, ICT setup and training complete at every site.
- Product hardening complete: load, cybersecurity and penetration testing, interface validation, deployment on KNPHI/DHA-approved infrastructure, with test reports available to the foundation.
- GHEC-AI escalation-to-response hand-off validated in live workflow — only authorised, minimum-necessary information passes.
- EOC staff trained at national and county level with training records and competency results (Output 4).
- Validated outbreak user guides, algorithms, workflow and training materials for all four categories (Output 5).
- AI model retrained on national EOC operational data, with a documented benchmarking and recalibration procedure and a published error and override log.
- Minimum event record published and adopted as a KNPHI standard.
Thresholds
- Dataset integration ≥ 80% of the baseline inventory
- AI–expert concordance ≥ 0.88 at every deployment site
- SUS ≥ 78 at every site
- Documentation completeness ≥ 85%
- Zero adverse decision events attributable to the AI layer
- Median signal detection → structured DMT-PHE classification ≤ 48 hours
- Measurable reduction vs. baseline in 7-1-7 detection and notification timelines at the national EOC and a majority of county sites
4Gate 3 — Evaluated, institutionalised and transitioned
Reporting period October 2028 – September 2029; verified at the final report; no payment attached. Decision: confirm close-out and inform any follow-on investment. Proposal
Milestones
- Prospective evaluation and endline assessment completed by WSU with KNPHI.
- KNPHI operational transition: system on Government infrastructure, admin rights transferred, maintenance, support and security procedures handed over.
- Recurrent budget pathway documented and reflected in a KNPHI budget submission or departmental statement.
- Scale-up evidence report and policy brief (Output 6).
- Two manuscripts submitted to peer-reviewed journals, with preprints.
- Regional dissemination through Africa CDC epidemic-intelligence networks and the WHO Preparedness Data Exchange.
- Open outputs released: de-identified/aggregated datasets, metadata, code, data dictionaries, model documentation.
Thresholds
- AI–expert concordance ≥ 0.90 · SUS ≥ 80 · documentation completeness ≥ 90%
- False-negative rate below the ceiling agreed at Gate 1
- Sustained reduction in detection-to-escalation latency vs. baseline
- Demonstrated improvement in 7-1-7 compliance vs. baseline at national and county sites
5Thresholds side by side
| Measure | Prelim. (Mar 2026) | Gate 1 | Gate 2 | Gate 3 |
|---|---|---|---|---|
| AI–expert concordance | 0.924 | ≥ 0.85 | ≥ 0.88 | ≥ 0.90 |
| System Usability Scale | 85.2 | ≥ 75 | ≥ 78 every site | ≥ 80 |
| Documentation completeness | — | ≥ 80% | ≥ 85% | ≥ 90% |
| Adverse decision events (AI) | 0 true risks | 0 | 0 | — |
| Dataset integration | — | inventory | ≥ 80% | — |
| Signal → classification (median) | — | baseline | ≤ 48 h | — |
| Detection → escalation latency | — | baseline | — | sustained ↓ |
| 7-1-7 compliance | — | baseline | ↓ vs. baseline | ↑ vs. baseline |
| False-negative rate | — | ceiling agreed | — | below ceiling |
See doc 12 for how each AI measure is defined, and doc 14 for data sources.
6How a gate decision is made
7Differences between the source documents
To settle at kick-off so everyone plans against the same numbers. Open
| Item | Proposal | Stage-gate paper | Deck | Suggested resolution |
|---|---|---|---|---|
| Number of county EOCs in Phase 2 | Five | Five | Four | Five (funding schedule); update the deck |
| Gate 2 concordance | ≥ 0.85 | ≥ 0.88 (rising standard) | ≥ 0.88 | 0.88, as the stage-gate paper proposes |
| Gate 2 SUS | ≥ 75 and ≥ 78 at all sites (both stated) | ≥ 78 every site | ≥ 78 | 78 at every site |
| Number of phases/gates | “Three-phase” approach, Phases 0–3 with four gated decisions | Three gates (Phases 0+1 combined) | Four phases, gates 0–3 | Three funding gates; keep Phase 0 → 1 as an internal go/no-go |
| MVP timing | Months 1–6 | Accepted by June 2027 (month 8) | Months 1–6 | Build in months 1–6; acceptance deadline 30 June 2027 |
| Phase 1 length | 6 months – 1 year | Ends Sept 2027 | Months 7–18 | Follow the stage-gate paper |
| 7-1-7 in gate thresholds | Gate 2 only | Added at Gates 2 and 3 | — | Follow the stage-gate paper |
8First 100 days
A suggested start plan, working back from the Gate 1 tests. Recommended
| When | Focus | Outputs |
|---|---|---|
| Weeks 1–2 (Nov 2026) | Kick-off and governance | Inception meeting; steering committee and TWG terms of reference; RACI agreed; recruitment of project coordinator and data analyst launched |
| Weeks 2–6 | Approvals on the critical path | DPIA drafted and lodged; KEMRI SERU amendment and WSU IRB extension submitted; DSA templates agreed; MOUs started for MVP sources |
| Weeks 3–8 | Data and MER | Dataset inventory for MVP sources; MER v0.1 workshop with KNPHI; baseline measurement protocol |
| Weeks 4–10 | Engineering foundations | Repositories, CI/CD, dev environment, synthetic data generator; ADRs 001–007 decided; GPU/server order placed |
| Weeks 6–14 | First vertical slice | One source (KABS or m-Dharura) → MER → signal card → digital DMT-PHE → logged decision, in development |
| By day 100 (early Feb 2027) | Checkpoint | Internal MVP review; GHEC-AI interface draft with Sobek; enterprise partner selected; risk register reviewed |
9Critical path
- Agreements and DPIA → no live data before they are in place.
- MER v0.1 → connectors, linker and DMT-PHE integration all depend on it.
- Baseline measurement → must happen before deployment changes behaviour; cannot be recreated later.
- Server/GPU procurement → staging and production depend on it; lead times can be months.
- MVP acceptance (30 June 2027) → leaves about three months for the eight-week parallel run and the Gate 1 report.
10Open questions
- Agree the reconciled numbers above and update all three source documents. Owner: PI + foundation · kick-off
- When exactly is the national parallel run? It must finish before the Gate 1 report. Owner: KNPHI + WSU
- What counts as “KNPHI acceptance” of the MVP? A signed acceptance protocol avoids ambiguity in June 2027. Owner: KNPHI + WSU
Sources
- Proposed Milestone-Based Stage Gates (WSU revision) — all gate milestones, thresholds and notes.
- INV-110654 proposal — Phased implementation steps; gated decisions.
- RADAR deck — slide 13 “Phased RADAR implementation”.