Washington State University · Global Health – KenyaRADAR Documentation
INV-110654 · Draft v0.1 · 29 October 2026
Doc 09·Operations

Deployment, Training & Adoption

How each EOC goes live: readiness assessment, ICT setup, training, the eight-week parallel run, go-live and ongoing support.

For: EOC & surveillanceLeadership & funderEngineeringStatus: Draft v0.1Updated: 29 October 2026

In short

  • RADAR rolls out to the national EOC first (Gate 1), then to five priority county EOCs (Gate 2).
  • Every site follows the same seven steps: readiness, ICT & access, training, an eight-week parallel run, go/no-go, live use, support.
  • The parallel run produces the concordance dataset by comparing RADAR and usual practice against a blinded expert panel.
  • Adoption is designed in: champions, less (not more) work for officers, fast support, and refreshers to counter staff turnover.

Why it matters

A technically excellent RADAR that county officers do not use fails every gate: SUS, documentation completeness and 7-1-7 all depend on real use. The JEE scored activation and coordination of personnel at the lowest level; uneven county readiness after devolution and frequent staff rotation are named gaps. Proposal Deployment and adoption need as much design as the software.

How this document connects

Labels used in this document: Proposal stated in the funded proposal, stage-gate paper or deck · Research external evidence (see Sources) · Recommended proposed design choice, to be confirmed · Open decision still needed

1Rollout sequence

WaveSitesTimingGate
0 · MVP demonstrationKNPHI PHEOC (test environment)By June 2027Gate 1 (MVP acceptance)
1 · NationalKNPHI PHEOC — 8-week parallel runMid-2027Gate 1
2 · CountiesFive priority county EOCs ProposalOct 2027 – Sep 2028Gate 2
3 · SustainAll sites under KNPHI operationOct 2028 – Sep 2029 (grant ends 31 Oct 2029)Gate 3

Choosing the five counties

Selection criteria to agree with KNPHI Recommended:

  • Outbreak burden across the four categories (e.g. cholera, RVF, VHF risk).
  • One Health relevance — pastoral and wildlife interfaces where animal signals matter.
  • Cross-border exposure — points of entry, neighbouring outbreaks.
  • Readiness — functioning county EOC, KABS and EBS coverage, connectivity, leadership commitment.
  • Overlap with DMT-PHE pilots — CGP reports that DMT-PHE pilot testing was planned in ten high-risk counties. Research
  • Diversity — include at least one county with weaker infrastructure so the design is tested where it is hardest.

2Seven steps per site

Readiness people, power, network ICT & access devices, accounts Training ToT + all users Parallel run 8 weeks, both paths Go / no-go thresholds met? Live use RADAR in routine use Support helpdesk, refreshers go no-go → remediate, extend WEEKS −6 TO −1 WEEKS 1–8 WEEK 9 ONWARDS Site order (proposal): national EOC first (Gate 1), then five priority county EOCs (Gate 2).
Every site follows the same seven steps. A site does not go live until its parallel run meets the gate thresholds; if it falls short, the team remediates and extends the parallel run rather than switching on early.

Site readiness checklist

AreaCheck
PeopleNamed EOC manager and site champion; surveillance officers identified for training; supervisor for review timers
WorkflowCurrent escalation path documented; DMT-PHE paper tools in use; baseline 7-1-7 and detection-to-classification measured
PowerGrid reliability; UPS or solar backup for EOC devices and network
ConnectivityMeasured bandwidth and uptime; Starlink installed where needed; fallback mobile data
DevicesLaptops/monitors per role (ICT supplies budgeted per period); browser versions; security baseline
AccessUser accounts with MFA; roles assigned; data-sharing agreements cover the county's sources
SupportHelpdesk contact known; escalation path for incidents; paper fallback procedure printed

3Training plan

AudienceLearnsFormat
EOC managers & incident managersSignal cards, confirming levels, overrides, 7-1-7 dashboard, GHEC-AI approvalsWorkshop + simulation exercise (SIMEX)
Surveillance officersVerification, event pages, recording actions, back-entryHands-on sessions, job aids, mentorship
Data analysts & stewardsQuarantine queues, merges/splits, data-quality dashboard, analytics configurationTechnical training
ICT administratorsAccounts, backups, monitoring, patching, incident responseRunbooks + shadowing the engineering team
Trainers (ToT)All of the above + facilitationTraining of trainers so KNPHI can train new staff after the grant
  • Competency assessment after training, with records kept — an Output 4 deliverable for Gate 2. Proposal
  • Outbreak user guides for all four outbreak categories, plus algorithms and workflow materials — Output 5. Proposal
  • Refreshers every six months and on-boarding packs for new staff, because rotation and infrequent events erode practice. Recommended
  • Simulation drills using RADAR's synthetic outbreak replay, so staff practise before a real event.

4The eight-week parallel run

Event same facts, same time Usual process EOC team + paper DMT-PHE · level, time RADAR + AI agent recommendation, citations, time Expert panel (blinded) reference classification Compare agreement · speed · completeness Concordance AI vs panel, usual vs panel Timeliness detection → classification Discrepancy log reviewed weekly
How the parallel run produces the concordance dataset. Each event is decided the usual way and, separately, by RADAR + DMT-PHE. An independent expert panel classifies the same event from the same facts without seeing either answer. Comparing both paths to the panel shows accuracy, speed and where they disagree — without risking a live decision on an unvalidated tool.

The proposal and stage gates require an eight-week parallel validation deployment of DMT-PHE at the national EOC, generating a concordance dataset against independent expert-panel review. Proposal Design points Recommended:

  • Blinding. Panel members see the same facts but not the AI or usual-practice answer. For the first weeks, keep the AI recommendation hidden from decision-makers (shadow mode) so the comparison is clean; reveal it once the protocol allows.
  • Enough cases. Real Level 2–3 events in eight weeks may be few. Pre-agree a minimum number of assessed events and top up with structured simulation cases and retrospective events so the concordance estimate is meaningful.
  • Pre-registered analysis. Define concordance (exact level agreement, plus a chance-corrected statistic such as weighted kappa), timeliness and documentation completeness before the run starts (doc 14).
  • Weekly discrepancy review. Every disagreement is reviewed by KNPHI and UM/CGHE; safety concerns stop the clock.
  • County runs repeat this in Phase 2, with AI retraining on national operational data in between.

5Adoption by design

Less work, not more

RADAR must remove re-typing and phone reconstruction. Measure time-on-task; cut any step that adds burden.

Site champions

One trained champion per EOC, first line of support and feedback channel.

Closing the loop

Show officers what happened to their signals and how their overrides improved the system.

Official backing

Update KNPHI SOPs so RADAR is the recognised record, not an optional extra.

6Support model

TierWhoHandlesTarget response
L1Site champion + CGP helpdeskHow-to questions, accounts, password resets, simple data fixesSame working day
L2KNPHI ICT / data stewardsConnector failures, data-quality issues, configurationNext working day; 4 h during an active Level 2–3 event
L3WSU / UM engineering, enterprise partnerBugs, outages, security incidents, model issues1 h for outages during an active event

Targets are a starting proposal Recommended; formalise in a support agreement before the first county go-live.

7Open questions

  1. Which five counties, and in what order? Owner: KNPHI · before Gate 1
  2. Minimum number of assessed events for the national parallel run. Owner: MEL + KEMRI · protocol
  3. Is shadow mode acceptable to KNPHI for the first weeks? Owner: KNPHI
  4. Who funds county connectivity and devices after the grant? Feeds the recurrent budget (doc 16). Owner: KNPHI + counties

Sources

  • INV-110654 proposal — Phase 1–2 descriptions; Budget (training materials, ICT, Starlink, participant reimbursements).
  • Stage-gate paper — Gate 1 milestone 4 (parallel validation); Gate 2 milestones 1, 4, 5.
  • RADAR deck — slide 7 (gaps: county readiness, workforce turnover); slide 14 (CGP role: rollout, training, helpdesk).
  • CGP — DMT-PHE validation and planned pilots.